Construction progress – Hills 14

The construction works at Hills 14 are progressing as planned. Piling and anchor installations have been successfully completed within the agreed timelines. Excavation is now finished, with the site reduced to foundation level.
The foundations have now started with the heads of the piles prepared for connection to the foundation.
Earthworks and excavation: 98%
Piling retaining works: 100%
Foundations: 10%
Construction progress – Málaga Centrum Apts

Málaga Centrum Apartments project has begun the construction of the guide walls, the preliminary structural works carried out before the diaphragm wall phase.