Construction progress Pinares de San Antón

Construction across the Pinares de San Antón development is moving ahead with solid progress:
Villa 1: Structure advancing from first to second floor.
Villas 3 & 4: Excavation complete, final levels reached.
Villas 4 & 5: Gabion retaining walls installed.
Villa 5: Pool structure underway; drainage and backfill in progress.
Villa 6: Structure rising steadily.
Villa 7: Structure complete; windows installed, brickwork done, and interiors underway.
Villa 8: Structural works nearly finished.
Villas 9 & 10: Ground floor structures progressing well.
Landscaping: Garden walls and terrace shaping ongoing, enhancing the site’s overall layout.
The project continues to take shape with each phase adding definition to this unique hillside development.