Construction at Alcalá 4 has started

We are excited to announce that construction at Alcalá 4 has officially started!
Our new project in the heart of Nueva Andalucía (Marbella) is underway.
The excavation phase has been successfully completed and we are now moving into the foundation stage.

Construction progress Pinares de San Antón

Construction across the Pinares de San Antón development is moving ahead with solid progress:
Villa 1: Structure advancing from first to second floor.
Villas 3 & 4: Excavation complete, final levels reached.
Villas 4 & 5: Gabion retaining walls installed.
Villa 5: Pool structure underway; drainage and backfill in progress.
Villa 6: Structure rising steadily.
Villa 7: Structure complete; windows installed, brickwork done, and interiors underway.
Villa 8: Structural works nearly finished.
Villas 9 & 10: Ground floor structures progressing well.
Landscaping: Garden walls and terrace shaping ongoing, enhancing the site’s overall layout.
The project continues to take shape with each phase adding definition to this unique hillside development.

Calle Bach is Now Under Construction

Construction has officially started at Calle Bach, located in Sierra Blanca, one of Marbella’s most exclusive residential areas.
Site preparation and groundworks are now underway, marking the transition from planning to execution.