QCT Management

Construction progress – Hills 14

The construction works at Hills 14 are progressing as planned. Piling and anchor installations have been successfully completed within the agreed timelines. Excavation is now finished, with the site reduced to foundation level.
The foundations have now started with the heads of the piles prepared for connection to the foundation.
Earthworks and excavation: 98%
Piling retaining works: 100%
Foundations: 10%

Projects update – Spring 2025

PROJECTS UPDATE — SPRING 2025
Here’s a look at how our current projects are shaping up:
🏡 Gate 3 (La Quinta, Marbella)
– Villa A: Sold.
– Villa B: This 5 beds and 5 baths luxury villa is now officially completed.
– Villa C: Luxury villa in the final phase of construction, featuring 5 beds and 6 baths
🏡 Alcalá 70 (Nueva Andalucía, Marbella) – Internal works advancing in this luxury villa with 5 beds and 5 baths; facades and technical installations near final stages.
🏡 Pinares de San Antón (Málaga) – Structure begins to rise for the construction of these 13 luxury villas, each featuring 3 to 5 beds and baths.
🏡 The Hills 14 (El Herrojo Alto, Marbella) – Retaining walls, foundations and site preparation for this luxurious 8 beds and 8 baths villa with a private sports club.
🏡 Málaga Centrum Apartments (Málaga) – First phase of construction: site preparation and retaining walls for the underground parking of these 35 luxury apartments, each with 2 beds and 2 baths.
🏡 Alcalá 4 (Nueva Andalucía, Marbella) – Construction has started for this luxury villa with 5 beds and 5 baths.

Construction progress – Alcalá 70

The construction of the villa at Alcalá 70 is progressing in line with the revised schedule:
Structure and foundations: 100% completed
Facades: brickwork and waterproofing at 95%
Technical installations: water, drainage, and electrical systems at 95%
Interior finishes: plasterboard partitions at 98%
External joinery: window installation at 20%
Landscaping: initial works completed in the lower garden