Construction progress – Alcalá 70

The construction of the villa at Alcalá 70 is progressing in line with the revised schedule:
Structure and foundations: 100% completed
Facades: brickwork and waterproofing at 95%
Technical installations: water, drainage, and electrical systems at 95%
Interior finishes: plasterboard partitions at 98%
External joinery: window installation at 20%
Landscaping: initial works completed in the lower garden

Gate 3: Villa B officially completed

Villa B in Gate 3 is officially completed and ready for sale. Construction is complete and all interior finishes are in place. Villa B showcases the quality and attention to detail that define the Gate 3 project. You can see the full project here.

QCT Management joins the Alliance for Childhood Vaccination

We are proud to be part of the Alliance for Childhood Vaccination alongside Gavi, the Vaccine Alliance, and Fundación “la Caixa”. Thanks to this initiative, we have contributed to vaccinating over 11 million children this year, ensuring a healthier future for them. Being part of this global effort strengthens our commitment to social responsibility and […]

Construction progress – Pinares de San Antón

We visited the construction of Pinares de San Antón, and its progress is remarkable. Design, luxury, and nature in perfect harmony. Discover the full project on our website. March 21, 2025 QCT Management