Construction progress – Alcalá 70

The construction of the villa at Alcalá 70 is progressing in line with the revised schedule:
Structure and foundations: 100% completed
Facades: brickwork and waterproofing at 95%
Technical installations: water, drainage, and electrical systems at 95%
Interior finishes: plasterboard partitions at 98%
External joinery: window installation at 20%
Landscaping: initial works completed in the lower garden

Gate 3: Villa B officially completed

Villa B in Gate 3 is officially completed and ready for sale. Construction is complete and all interior finishes are in place. Villa B showcases the quality and attention to detail that define the Gate 3 project. You can see the full project here.