Construction progress – Alcalá 70

The construction of the villa at Alcalá 70 is progressing in line with the revised schedule:
Structure and foundations: 100% completed
Facades: brickwork and waterproofing at 95%
Technical installations: water, drainage, and electrical systems at 95%
Interior finishes: plasterboard partitions at 98%
External joinery: window installation at 20%
Landscaping: initial works completed in the lower garden